Advertising Networks of Florida

TS Andrea packs light punch, but 2 boats hit BB pier

By Mark Young, Islander Reporter

Bradenton Beach public works employees secure a boat that broke anchor and crashed into the Historic Bridge Street Pier June 6 during the brush with Tropical Storm Andrea. No one was aboard the vessel. Islander Photo: Mark Young

A man on the Grand Finale double checks his anchor June 6 during Tropical Storm Andrea in Sarasota Bay south of the Historic Bridge Street Pier. Two boats broke loose from their moorings and hit the pier. Most boaters took precautions and secured their crafts. Islander Photo: Mark Young

It was a familiar sight at the Bradenton Beach Historic Bridge Street Pier June 6 as Tropical Storm Andrea’s outer storm bands made their way across Anna Maria Island.

The storm’s impact was less than last year’s Tropical Storm Debby, although beach erosion was evident. It was, however, déjà vu at the city pier, where workers scrambled to protect the structure from wayward boats.

Two boats broke loose from their anchorage in Sarasota Bay and crashed into the pier during Andrea, while TS Debby sent more than a half-dozen boats crashing into the pier deck and pilings.

City officials were relieved to learn most boaters had secured their crafts, although there was enough damage to temporarily close the outer half of the pier.

A 30-foot sailboat hit the pier, but caused little damage, according to Bradenton Beach Police Chief Sam Speciale. The owner was quickly located and the boat was removed.

A 20-foot sailboat caused significant damage to a lengthy section of railing, cracked a concrete piling and loosened the pier’s center copula.

Speciale said the boat first hit the protective pilings near the floating dock, but continued to slide and hit the pier as the storm pushed it toward the Intracoastal Waterway, scraping and bumping the pier as it went.

About 30 feet of railing was loosened, there was some light damage to the wood deck of the pier and the copula will likely be removed before the pier reopens.

The copula was scheduled to be removed during the upcoming pier renovation project, according to public works director Tom Woodard, and there’s no sense in spending money to repair it.

Woodard said he didn’t expect the eastern half of the pier to remain closed for long.

“It shouldn’t be more than a couple of days,” he said. “The railing needs to be fixed and my guys will take down the copula. The one area of concern is the cracked piling and just how badly damaged it is.”

The pilings will be replaced during the renovation project, but if the integrity of the pier is jeopardized and there’s a safety issue, the closure could be longer.

“I don’t think that will be the case,” said Woodard. “We’ll get out there after the storm and do a better inspection and we’ll have a better idea at that time.”

The good news is that the floating dock adjacent to the pier endured its first test in the choppy waters of the bay as Andrea passed. The new hinges acted as they should, according to BBPD Lt. John Cosby.

“It did real well and everything did what it was supposed to do,” said Cosby. “And fortunately, none of the boats hit the floating dock.”

The floating dock was closed for more than a year when faulty hinges first created a safety issue because sections began to separate. Debby’s arrival ensured its long-term closure by causing further damage.

The floating dock reopened a week prior to Andrea, but held up well and remains open.

City workers secured the 20-foot sailboat that caused most of the damage to the pier until the owner could be contacted.

After securing the pier, Speciale updated commissioners at the June 6 city pier meeting.

“The public works guys got it handled,” said Speciale. The guys did a great job and got out there as soon as we called them. I really believe there would have been a lot more damage if they had not got there as quickly as they did.”

Mayor John Shaughnessy asked for an update on the pier renovation project.

Building official Steve Gilbert said the project remains on schedule.

“I spoke to the lead engineer of ZNS Engineering,” said Gilbert. “We should have drawings in the next couple of weeks. As soon as we have the drawings, we’ll be ready for the scope of work and request for proposal.”

Gilbert said the permitting process through the Florida Department of Environmental Protection and U.S. Army Corps of Engineers is expected to go smoothly, but said that could be the only issue in pushing the project beyond a targeted August completion.

“The only unknown is the DEP and corps and what they will do,” said Gilbert. “The project consists of pilings going back into the same holes, so common sense says it shouldn’t be a problem.”

One Response to TS Andrea packs light punch, but 2 boats hit BB pier

  1. Sophia says:

    Quit playing around with worrying about rental unit, 1st floor occupancy and other non-life threatening issues and put the mooring fields in. Before this ends up killing someone. Yes, these people are very much a part of our community, but they also are living free and without responsibility. Put the mooring field in, keep them & the pier safe. If they can find money for beer & cigs they can come up with a rental fee to live at the bay.

Leave a Reply

Your email address will not be published. Required fields are marked *

CAPTCHA Image

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Join Our Mailing List


Sign up for breaking news notices and weekly news and classified reminders via your e-mail.

To advertise here, please
visit our rates page
or contact us at:
sales@islander.org
Phone: (941) 778-7978
Fax: (941) 778-9392

 Newspapers  Newspapers  Newspapers  Newspapers  Newspapers