Suspense builds for pier-Mote center

thumb image
Eric Wilson and his son, James, 5, wait for the fish to bite while visiting the Anna Maria City Pier, 100 N. Bay Blvd., Anna Maria, during a February vacation from Oklahoma. Islander Photo: Ryan Paice

The building at the T-end of the Anna Maria City Pier has stood empty since the pier was rebuilt two years ago.

And it will remain empty for a while more.

City clerk LeAnne Addy announced via email March 1 that the city canceled a March 8 special meeting to discuss Mote Marine Laboratory’s plans for an educational outreach center to fill the space.

Mote agreed in September 2021 to lease the empty 1,800-square-foot empty space on the pier and more recently has been planning the interior.

Mote’s options include:

  • Creating a center with four marine live display tanks featuring different fish and crustaceans visitors can view and touch;
  • Creating a center with interactive media displays such as a livestream underwater video from beneath the pier.

Mayor Dan Murphy has said both options would be considered if the pier passes a structural inspection needed to add display tanks.

Murphy wrote in a March 3 email to The Islander that the March 8 meeting was canceled because the city “did not receive the inspection report in time for the commission to review the results.”

He said Sarasota-based Infrastructure Solutions Services had not completed the inspection as of March 3 but it should be finished by the week beginning March 7.

Murphy added that a meeting with Mote would be rescheduled as soon as possible “once we have all the necessary documents in hand.”