- City center in Holmes Beach: Work on the city’s project near the intersection of Gulf and Marina drives is not concluded. Traffic patterns can change. For the latest, check the city’s page on Facebook.
- 64th Street at Marina Drive in Holmes Beach: A road closure for work on stormwater drainage was planned to begin July 18.
- Gulf Drive in Bradenton Beach: Manatee County is moving sewer lines along Gulf Drive from Sixth Street South to 11th Street South and on side streets. For the latest, go to amiprojects.io.
- AMI Bridge on Manatee Avenue/State Road 64: Repair and rehab work will begin on the bridge Monday, July 24, with temporary overnight single-lane closures 7 p.m.-6 a.m.
A fact sheet from the Florida Department of Transportation said improvements include coating steel members, restoring section loss on corroded steel members, repairing, adjusting and testing the mechanical system that raises and lowers the bridge’s bascule segments, performing crack injections and cleaning corrosion and painting of the structure.
The cost is estimated at $1.1 million.
In addition to lane closures, people should expect noise from construction equipment.
The estimated completion is winter.
For area road watch information, go online to swflroads.com or dial 511.